Dojo Renovation
Milford, CT
Sep 2010-May 2011
September
October
Prep work

*  Water heater moved.
*  HV/AC moved.
*  Oil Tank moved

Replace poles with steel
beam

Bathroom framed,
plumbed, sheetrocked

Outside walls framed

New stairs
November
December
Sheetrocked stair walls

Working bathroom

Sheetrocked dojo walls

Installed sub-floor

Painted bathroom and
dojo walls

Prepped hardwood for
installation
January
February
Added wall treatments
to Shomen (front)

Installed mirrors
March
April
Installed hardwood floor

Installed shomen floor

More wall treatments

Installed dojo doors
May
Finished hardwood floor
and added Goju Ryu
lettering

More wall decor